DFCI Merrimack Valley

Project Info

  • Location

    Methuen, MA

  • Size

    60,000 sq. ft.

  • Owner

    Dana Farber Cancer Institute

  • GC

    Consigli Construction Company

  • Contract Price

    $4.6 million

Project Scope:


The project included a fast-track 8-month schdeule that was compressed 10 weeks to accommodate Dana Farber’s occupancy requirements. Complex systems that are unique to Dana Farber were also added too our scope, which required a massive team effort amongst all trades in order to hit key timeline milestones.
 

Project Overview


    • Renovation of existing office space for a new outpatient facility which includes 24 exam rooms and 32 infusion bays.
    • Among its many features, the facility included a specialty Clean Room lab. The clean room is a fully modular, prefabricated system, inclusive of walls, ceiling and ceiling suspension which required pinpoint accuracy for our power and lighting install.
    • Lynnwell completed the install of all life safety power, new switchgear with four transfer switches, lighting and lighting controls, fire alarm system, security system, telecommunications system, Audio Visual system, CAMS system, RTLS system and Nurse Call system.